The Kerala High Court has approved strict measures to prevent pollution of the Pamba River during the annual Mandala-Makaravilakku pilgrimage to Sabarimala. The measures include penalties of up to ₹5,000 for people found polluting the river by dumping clothes, plastic or other waste.
The court upheld an order issued by the Additional District Magistrate (ADM), which prohibits activities that contaminate the river and allows fines to be collected on the spot from violators. It observed that effective enforcement of the restrictions is essential to protect the river’s cleanliness and that negligence in this regard cannot be tolerated.
A Division Bench comprising Justice Raja Vijayaraghavan V and Justice K.V. Jayakumar passed the directions while considering a report submitted by the Sabarimala Special Commissioner and related proceedings. The matter was taken up on the basis of Special Commissioner Report No. 32/2026.
The court observed that the ADM’s order under Section 163 of the Bharatiya Nagarik Suraksha Sanhita (BNSS), 2023, was consistent with earlier judicial directions aimed at preventing the uncontrolled dumping of waste and other pollutants into the Pamba River.
Court Flags Serious Gaps in Sewage Treatment and Waste Management
During the hearing, the Travancore Devaswom Board (TDB) informed the court that awareness campaigns were being conducted to discourage pilgrims from throwing clothes and other materials into the river.
However, after examining an inspection report submitted by the environmental engineer of the Kerala State Pollution Control Board (KSPCB), the High Court identified several shortcomings in sewage treatment, solid waste management and river-cleaning arrangements.
The court noted that the functioning of the sewage treatment plants (STPs) required immediate improvement. The Pollution Control Board had directed the Devaswom Board to remove accumulated sludge from all STP tanks and ensure their thorough cleaning.
It also recommended restoring all four clarifiers, filters, pumps and treatment units to their prescribed operating capacities. Technical defects in chemical dosing systems, flow meters, pH meters, electrical panels, blowers and pumps must also be repaired. The entire system should undergo proper technical certification to ensure that it is functioning effectively.
Incinerators Need Repairs and Better Waste Segregation
The Pollution Control Board’s report also raised concerns about the condition of the waste incineration plant and recommended comprehensive improvements.
Repairs are required in the machine’s switches, diesel pump and blower. The roof of the incinerator building also needs to be replaced promptly to prevent rainwater from entering and affecting the equipment’s performance.
The Board emphasised the need to segregate waste into separate categories, including biodegradable, recyclable and non-recyclable materials. It recommended that unsorted waste, plastic and PET bottles should not be directly fed into incinerators.
The report further stressed that trained personnel should be assigned responsibility for operating the machines to ensure proper handling and reduce operational problems.
FCRF Launches Certified Chief Risk Officer (CRO) Program for India’s Risk Leaders
Special Arrangements Proposed for Flowers and Discarded Clothes
During the proceedings, the Pollution Control Board’s standing counsel informed the court that flower waste was also being dumped into the incinerator, affecting its efficiency.
As a possible solution, the Board suggested engaging organisations involved in flower-waste recycling. It also recommended deploying permanent cleaning staff at Pamba Arattukadavu and nearby riverbank areas to collect clothes discarded by pilgrims.
On the disposal of collected clothes, the Devaswom Board informed the court that a contractor had been appointed to transport the material to Clean Kerala Company Limited (CKCL).
However, the High Court sought clarity on the contractor’s responsibilities and the complete process for transferring the collected clothes to the company. It also asked the Board to explain the mechanism through which the collected material would be handed over.
Police Mess Approved for 183 Healthcare Workers
The hearing also covered arrangements for healthcare personnel deployed during the pilgrimage. The Special Government Pleader informed the court that approval had been granted to provide police mess facilities to 183 permanent medical and paramedical staff members.
A request to extend the facility to other employees, including personnel associated with the panchayat, will be considered after a formal application is submitted.
The High Court directed the Devaswom Board’s counsel to obtain detailed information about improvements in cleaning arrangements, the disposal of flower waste and action taken on the Pollution Control Board’s recommendations.
The matter is scheduled for its next hearing on December 8. The court’s directions seek to strengthen pollution-control measures and improve waste management during the Sabarimala pilgrimage, when large numbers of devotees visit the Pamba River.